Project Update

There has been a delay in getting the contractor to site to complete the remaining car park works (last layer of asphalt and line marking) and we are caught up in the demand for road contractors to fix storm damage.

At this stage the asphalt is scheduled for Friday 9 December, but as there is a risk it could get pushed back into next week. The remaining works are not impacted and would be ready to open on 9 December, but with the car park delay, the opening will be delayed. Plus, the car park would need to be closed for 1 day next week to undertake the line marking.

Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>