Construction works are progressing with all subsurface works completed.

Due to wet weather delays, and contractor availability, the construction works are scheduled to be completed in mid-November 2022. This date also takes into account the expected further wet weather delays.

In the attached images below you can see the completed viewing platform, stage and car park kerb. The light pole has also been removed and the contractor has taken delivery of the landscaping materials (sandstone blocks).