Update
Procurement of pedestrian fencing has commenced. Concrete works for widening and realigning the existing path are expected to commence in two weeks. Installation of the pedestrian fencing should take place one week after the school holidays, subject to confirmation from the fencing contractor.
Also progressing in the background is the pedestrian crossing upgrade design, in conjunction with traffic data that has been collected for the continuing investigation and development of intersection improvements at South Street and St Vincent Street.