Project Update
The completed construction activities to date include:
- Bulk earthworks on oval.
- Installation of inground electrical cabling.
- Installation of inground services and stormwater drainage.
- Erection of main field light towers.
- Installation of kerb perimeter around the oval.
- Croquet building: Structural Frames and all internal wall frames have been completed.
- Off-street carpark: Asphalt works has been completed, water bollards removed, landscape areas mulched, and zone handed back to the public.
- AFL Building: wall sheets, brickwork and Glazing has been completed
- Croquet building: Rough in has commenced and the roofing works have been completed.
- Off-street carpark: Area has been completed and handed back to the public. Line marking to be completed at the end of the project.
- Water has been connected into site with all inground lines now charged up to the irrigation system.
AFL Building - 21 September 2022