Moss Vale Road Water Infrastructure - Update
August - September 2022 Update
-
Package 1: Stage 1 Water Main Lead-in Work (Completed 2021)
- Package 1 works completed 2021.
-
Package 2: Illaroo Road Water Pumping Station Upgrade
- Detailed design completed June 2022, with procurement activities to follow 2022/2023.
- Pre-work vegetation removal undertaken
- Power supply works undertaken.
-
Package 3: Stage 2 Water Mains (new and upgrades)
- Detailed design completed April 2022, with procurement activities to follow 2022/2023.
-
Package 4: New Water Reservoir Cambewarra
- Detailed design completed March 2022, with procurement activities currently in progress.
Image: Water Pipeline
Share Moss Vale Road Water Infrastructure - Update on Facebook
Share Moss Vale Road Water Infrastructure - Update on Twitter
Share Moss Vale Road Water Infrastructure - Update on Linkedin
Email Moss Vale Road Water Infrastructure - Update link