Illaroo Road Update - December 2020

The kerbing has been completed on the new roundabout at Illaroo Road and West Cambewarra Road. Installation of the utilities is nearing completion.

Due to the unfavourable weather conditions recently, the pavement will be constructed after the Christmas break.

During the Christmas break two way traffic will be open with traffic management signs and water barriers in place to direct traffic. The speed will be limited to 20km/hr.