Works Update
The principal contractor to Bioelektra Australia, EQ Constructions, has advised they are no longer available to complete Stage 1 Works at the West Nowra site.
This development has Bioelektra Australia re-tendering to finish the Stage 1 construction works, which are largely complete.
Bioelektra Australia’ s Managing Director, Fred Itaoui, released the following statement:
“The construction works at our West Nowra Resource Recovery Facility are currently at a standstill due to the collapse of the builder EQ Constructions. Bioelektra Australia has put out a tender to appoint another builder to complete the construction works of the facility. This unfortunate event has regrettably hindered the construction programme by at least 3 months.”
Once the new contractors are appointed, Council looks forward to watching this exciting development take shape.