Update
Batmac Constructions have completed the block work on the amenities block and the roof framing is underway.
Contract negotiations are being carried out with the preferred contractor for the beach access ramp following an onsite meeting was held on 25 February 2021 to review the levels and set out of the ramp.
The final link paths and accessible parking will be completed at the end of the project.